Earned value management(EVM)integrates the scope baseline with the ()baseline,along with Schedule baseline,to form the performance baseline,which helps the project management team assess And measure project performance and progress

Earned value management(EVM)integrates the scope baseline with the ()baseline,along with Schedule baseline,to form the performance baseline,which helps the project management team assess And measure project performance and progress

发布时间:2025-12-02 05:05:27
推荐参考答案 ( 由 专技宝 官方老师解答 )
答案:cost